- in Grants.gov
- Continue formulating/drafting Project Narrative
- If STTR and RI not determined yet, continue to work on establishing partnership with appropriate RI.
- Begin to formulate budget. Try to determine as early as possible if subcontractors, consortia, or other partnerships will be necessary to carry out proposed R&D.
|
4 | FOA Released - Locate appropriate FOA in grants.gov, download, and review for application requirements & specifics
- Finalize senior / key personnel and begin completing biosketches
- Begin completing Current & Pending Support for PI and key / senior persons
- Begin drafting LOI
- Continue drafting Project Narrative
- If working with a service provider or reviewer, begin providing Project Narrative sections for review as they are completed for comments
|
5 | - Finalize partnerships with RI, consortia, and any partnering organizations
- Continue drafting Project Narrative
- Continue to formulate budget
- Review PIER Plan requirements and begin formulating PIER Plan
- Review Commercialization Plan requirements and determine if outside assistance from service provider needed
|
6 | - Verify SAM registration complete
- Submit LOI in PAMS
- Begin entering information on the SF424 webform in Grants.gov
- Register as SBA on SBIR.gov
- Request letters of commitment/funding/support from RI, consortia, and/or any partnering organizations
|
7 | LOI due - Finalize biosketches for PI and all senior/key persons
- Continue drafting Project Narrative
- Continue to formulate budget
- Divide time between creative aspects of writing Project Narrative and completing required forms - R & R Senior/Key Person Form, R&R Other Project Information Form, SBIR/STTR Information Form.
|
8 | - If partnering with RI or any subcontractors, send subaward budget documents (downloaded from grants.gov application workspace) to RI or representative for completion
- Continue drafting Project Narrative
- Continue to formulate budget
- Begin Budget Justification Form
- Determine data management plan; if working with an RI, ensure that there is agreement on how/if data is to be shared
|
9 | - Continue drafting Project Narrative
- Continue to formulate budget
- Divide time between creative aspects of writing Project Narrative and completing required forms - R & R Senior/Key Person Form, R&R Other Project Information Form, SBIR/STTR Information Form.
- Complete Level of Effort and Max Funding spreadsheet
- Review DOE application checklist to ensure all required forms have been completed
|
10 | Non-responsive feedback, if any, issue - If you receive non-responsive feedback, review, address the comments, and determine next steps
- Begin finalizing Project Narrative
- Begin finalizing Budget
- Review subaward budgets (if any) from RI and/or subcontractors
- Finalize PIER Plan
- Finalize Commercialization Plan
- Finalize Budget Justification Form
|
11 | - Review Project Narrative for necessary edits and/or adjustments
- Review Budget for any errors or inconsistencies
- Review Budget Justification to ensure consistency with Budget
- Review DOE checklist to ensure all necessary forms completed
|
12 | Submit application |
13 | Full application due |