Week 

Activities - 8 Week Calendar 

1 

FOA Released 

  • Locate appropriate FOA in grants.gov, download, and review for application requirements & specifics 
  • Determine type of application:  SBIR, STTR, or Both
  • Research issuing office - review mission, needs, research, programs 
  • Assess ability to successfully respond to FOA
  • Begin PAMS registration
  • Locate service providers - SBDC, PTAC, etc.
  • Contact Topic Author/Manager if you have questions
  • Download DOE SBIR/STTTR application checklist

2 

  • If STTR application, or working with RI, consortia, or any partnering organizations, begin contacting those organization if known.  If you do not have established contacts, review partnering resources. 
  • Continue contacts with service providers if necessary
  • Draft LOI
  • Begin SAM registration
  • Begin drafting Project Narrative 

3 

  • Continue working on SAM registration
  • If working with an external reviewer, submit narrative elements completed thus far and seek feedback
  • If working with an external reviewer, submit LOI draft and seek feedback
  • Begin thinking about, and formulating, the budget if possible
  • Request letters of commitment/funding/support from RI, consortia, and/or any partnering organization  
  • Consider personnel and/or partnerships required to respond
  • Begin considering PI and the role they will take in the project
  • Continue drafting Project Narrative 
  • Continue to formulate budget 
  • If working with a service provider or reviewer, begin providing Project Narrative sections for review as they are completed for comments 

4 

LOI due 

  • Submit LOI in PAMS 
  • Continue considering personnel and/or partnerships required to respond
  • Review and download commercialization plan
  • Continue drafting Project Narrative 
  • Continue to formulate budget 
  • Begin to format biosketches & current / pending support
  • Divide time between creative aspects of writing Project Narrative and completing required forms - R & R Senior/Key Person Form, R&R Other Project Information Form, SBIR/STTR Information Form.   
  • Consider/determine necessary letters of commitment/funding/support from RI, consortia, and/or any partnering organization 

5 

  • Begin Grants.gov registration
  • Confirm PI
  • Once registered with Grants.gov, create workspace and download application package and begin completing forms
  • Continue considering personnel and/or partnerships required to respond
  • If partnering with RI or any subcontractors, send subaward budget documents (downloaded from grants.gov application workspace) to RI or representative for completion 
  • Request Requests letter of support
  • Draft Commercialization Plan
  • Review PIER Plan requirements and begin to formulate plan
  • Continue drafting Project Narrative - get feedback on completed sections
  • Begin to formulate budget 
  • Begin Budget Justification Form 
  • Request biosketches for personnel and current/pending support lists
  • Determine data management plan; if working with an RI, ensure that there is agreement on how/if data is to be shared 

6 

  • Register as SBC on SBIR.gov
  • Follow up with RI or any subcontractors regarding required forms
  • Follow up on requested Letters of Support
  • Reach out to appropriate partners regarding PIER Plan
  • Draft PI Biosketch and Current & Pending funding
  • Finalize key personnel
  • Continue drafting Project Narrative - get feedback on completed sections
  • Continue to formulate Budget 
  • Continue to draft Budget Justification
  • Draft Project Abstract / Summary
  • Proof biosketches received so far
  • Get feedback as necessary for Grants.gov and other required forms
  • Divide time between creative aspects of writing Project Narrative and completing required form
  • Review DOE application checklist to verify all required forms

7 

Non-responsive feedback, if any, issue 

  • If you receive non-responsive feedback, review, address the comments, and determine next steps 
  • Finalize Grants.gov forms
  • Get feedback on Budget
  • Get feedback on Budget Justification 
  • Secure required forms from RI and any partnering organizations or subcontractors
  • Secure Letters of Support
  • Get feedback on Project Narrative
  • Draft PIER Plan 
  • Finalize Commercialization Plan
  • Continue to proof biosketches

8 

  • Review Project Narrative for necessary edits and/or adjustments 
  • Review & finalize Budget 
  • Review & finalize Budget Justification
  • Review DOE checklist to ensure all necessary forms completed 

9 

Finalize & Submit application 

...