1. PAMS will send an email notification to the PI indicating that the task has been created (Figure 1). Follow the Portfolio Analysis and Management System (PAMS) link provided in the email. OR Log in to the PAMS external website at http://pamspublic.science.energy.gov.

Image Modified

Figure 1. PAMS Email Notifications – Existing PI, Progress Report Task


Image Added

For guidance on logging in, refer to Logging In.


2. Once you are logged in to PAMS, navigate to the Tasks tab > Pending Tasks – List page (Figure 2).

Image Modified

Figure 2. Tasks – Pending Tasks – List Page, Start Progress Report

3. Find the Submit Progress Report task you want to complete, and click the Start Progress Report link in the Options column (Figure 2). If necessary, use the filters in the grid or click the Search link on the right above the grid to find a specific Submit Progress Report task to work on.

...

1. If the PI does not have an existing external PAMS account, PAMS will send an email notification to the PI indicating that the task has been created, and provide a registration link and code (Figure 3). Click the I do not have a PAMS account link.

...

Figure 3. PAMS Email Notifications – No Existing PI, Progress Report Task

2. Enter the registration code on the Verify Registration Code page, and click Verify in the bottom right corner of the page (Figure 4).

Image Removed

Figure 4. Verify Registration Code Page

3. Complete the account creation process. (Step-by-step instructions for account creation can be found in the External User – Create Account training module.)

4. Begin at Step 2 in section 1.1 Existing Account to access the Progress Report task after creating the account.

The user will be navigated to the PAMS login page. For guidance on creating a PAMS account with a registration code, refer to Create/Update a User Account.

3.2 Reviewing Progress Report 3.2 Reviewing Progress Report Status

When you select a progress report on the Pending Tasks – List page, PAMS redirects you to the progress report’s Progress Report – Status page. The Progress Report – Status page shows the completion status of each section of the progress report. The sections are listed in the left navigation menu and in the Progress Report Status section on the page.

Sections that are complete will display “Complete” with a green checkmark in the Status column. Sections that are not complete will display “Not Started” or “In Progress” with a green checkmark with a red slash through it in the Status column.

Image RemovedImage Added

Figure 54. Progress Report – Status Page 

3.3 Completing the Cover Page

The Cover Page always has a status of “Complete”, because the information in this section prepopulates with information from the Award record. Use the following steps to review and edit the Cover page.

1. Navigate to the Cover Page by clicking Cover Page in the left navigation menu or by clicking Update in the Options column on the Progress Report – Status page (Figure 5).

2. PAMS will load the Progress Report – Cover Page. On this page, you can add, edit, or delete the Recipient Award Identification Number (Figure 6).

...

Image Removed

...

The Recipient Award Identification Number is a number issued by the recipient and used for internal processing or reporting.

Image Removed

Figure 6. Progress Report – Cover Page

...

Image Removed

...

Because the Award and PI Information prepopulate from the Award record, you cannot edit them on the Cover Page. To edit this information, you must create an Award Modification Request. (For guidance on creating an Award Modification Request, refer to How To: Create Award Modification Request.)

Page


Image Added

 

3.3 Completing the Cover Page

The Cover Page always has a status of “Complete”, because the information in this section prepopulates with information from the Award record. Use the following steps to review and edit the Cover page.

1. Navigate to the Cover Page by clicking Cover Page in the left navigation menu or by clicking Update in the Options column on the Progress Report – Status page.

2. PAMS will load the Progress Report – Cover Page. On this page, you can add, edit, or delete the Recipient Award Identification Number.

Image Added

The Recipient Award Identification Number is a number issued by the recipient and used for internal processing or reporting.

Image Added

Figure 5. Progress Report – Cover Page

Image Added

Because the Award and PI Information prepopulate from the Award record, you cannot edit them on the Cover Page. To edit this information, you must create an Award Modification Request. (For guidance on creating an Award Modification Request, refer to How To: Create Award Modification Request.)

3. Once you have completed the Cover Page section, click Mark as Complete in the bottom right corner of the page.

Image Added

For any page with a Choose Action dropdown:

  • Select Save from the Choose Action dropdown to save your progress at any time without leaving the page.
  • Select Save and Continue from the Choose Action dropdown to save your work and continue on to the next section.
  • Select Mark as Complete from the Choose Action dropdown to mark the section as complete and continue on to the next section. All sections must be marked as complete before you can submit the progress report.

Click Go to Previous Section in the bottom left corner of the page to return to the previous section without saving your progress.

4. PAMS will redirect you to the next section and display a Success message confirming that the Cover Page was marked as complete successfully.

Image Added

Figure 6. Cover Page Success Message

3.4 Completing the Accomplishments Section

The Accomplishments section of the progress report records the project’s performance over the duration of the award. This performance is tracked with a list of six questions pertaining to project goals, accomplishments, training and development opportunities, dissemination of results, and goals and intentions for the next reporting period. Use the following steps to complete the Accomplishments section of the progress report.

1. Fill in each textbox as appropriate. If applicable, you can select the “Nothing to Report” or “No Change” radio buttons and leave the accompanying textbox empty.

Image Added

Figure 7. Progress Report – Accomplishments

Image Added

  • You can attach one document in the Accomplishments Attachment section at the bottom of the page by clicking the Attach File button on the far right of the section header, browsing, and clicking Upload.
  • You can also include a description of 500 characters or less in the Accomplishments Attachment Description box. To edit the description or delete the attachment, click the Actions dropdown and select the appropriate action.

2. Once you have completed the required fields, select Mark as Complete from the Choose Action dropdown and click Go.

3. PAMS will load a Success message confirming that the Accomplishments section has been marked as complete successfully.

Image Added

Figure 8. Progress Report – Accomplishments Success Message 

3.5 Completing the Products Section

The Products section of the progress report inventories all products created during the course of the project. There are twelve Product types:

  • Publication – Journal Article
  • Publication – Book
  • Publication – Book Chapter
  • Publication – Thesis/Dissertation
  • Publication – Conference Paper/Presentation
  • Publication – Website
  • Publication – Other Publication
  • Intellectual Property – Patent
  • Intellectual Property – Invention
  • Intellectual Property – License
  • Technologies or Techniques
  • Other Products

Image Added

Figure 9. Progress Report – Products


Image Added

For Labs Awards, PAMS will display an "Additional Products (Response for DOE)" section below the "Other Products" section.


3.5.1 Adding Products for Non-Lab Awards

1. To add or update Products for non-Lab Awards, click the Add/Update Products link above the Publications section on the Progress Report – Products page. PAMS will navigate to the Products – Add/Update Products page, which displays a list of Products associated with the Award.

Image Added

Figure 10. Products – Add/Update Products

Image Added

  • Products that have been reported on previously submitted Awardee Reports (i.e., created and reported in the last Awardee Report before this Progress Report was created) will display with a grayed-out selected checkbox. You cannot remove these Products from the batch cart until the current project period ends.
  • Any Product(s) you add now will be selected for inclusion in the Progress Report by default, but you may unselect them before returning to the Progress Report – Products page.
  • All Products must be added/updated in E-Link.
  • Products deleted in E-Link are moved to an "Archive" status. These Products are reflected in PAMS with a "Deleted in E-Link" status.
  • If the Awardee report is completed before returning to PAMS, some newly added/updated Products may be missing from the submitted Awardee report. These Products will still be reported as STI and appear in PAMS on your Award Products – List page.
  • Any Products that have been merged into an E-Link sourced Product will display as a read-only record in the detailed view for the Product with which they were merged.
  • E-Link Products that have been retained after merging with a different Product record will have an "Enhanced by OSTI" status in the "Current Product Status" column.
  • You can view the information for a specific Product by click the View Product link in the Options column for the Product.
  • You can view a complete list of Products selected for inclusion in the Progress Report by clicking the View link in the page actions bar below the Resources header. PAMS will open the View Selected Products page in a new tab.

2. To add a new Product, click Add/Update Product in E-Link.

3. PAMS will display a Confirmation overlay stating that the user will be redirected to E-Link. Click Confirm.

Image Added

Figure 11. Products – Add/Update Products, Navigate to E-Link Confirmation


4. PAMS will navigate to E-link. Add/update Products in E-Link as necessary. For E-Link specific guidance, you may visit: 

5. When you are finished, click the "Return to PAMS" button. E-Link will return you to the Products – Add/Update Products page, where PAMS will display a Note detailing the last Product data sync.

Image Added

Figure 12. Products – Add/Update Products, Sync

3.5.2 Adding Products to the Report

1. Review the list of Products on the Products – Add/Update Products page to ensure the correct Products are selected for inclusion on the progress report. When you are ready, click Save and Continue in the bottom right corner. PAMS will return to the Progress Report – Products page and display a green success message confirming that the Products list has been updated successfully.

Image Added

You can remove Products on the Progress Report – Products page by selecting the Remove from Report action in the Action menu for the Product.

3.5.3 Adding Products for Lab Awards

1. To add or update Products for Lab Awards, click the Add Products to Report link above the Publications section on the Progress Report – Products page. 

Image Added

Figure 13. Progress Report – Products, Add Products to Report


2. PAMS will navigate to the Products - Select Award Products page, which displays a list of Products available to associate with the awardee report. To add Products from OSTI.gov, click the Add Products to Award from OSTI.gov link below the Resources header. 

Image Added

Figure 14. Products - Select Award Products


Image Added

If a Product was approved on a previously submitted Lab Awardee Report and was prepopulated on the current Awardee Report, the checkbox for that Product will be selected by default and you will not be able to deselect it.


3. PAMS will navigate to the Products – Add Products from OSTI.gov page. This page allows you to search for and select STI Products from OSTI.gov to associate to your Lab Award. Selected Products will be linked to your Award record for tracking and reporting purposes. To locate a Product, enter at least one search parameter in the basic or advanced search parameters and click the Search button. 

Image Added

The following product types are not eligible to return in the search results at this time: Technical Report, Software, Program Document, Video/Audio, Miscellaneous

Image Added

Figure 15. Products – Add Products from OSTI.gov


4. PAMS will reload the page with search results from OSTI. Once you have found the Product you would like to associate to your Award, select the checkbox associated to that Product and click Save and Continue in the bottom right corner. 

Image Added

Figure 16. Products – Add Products from OSTI.gov, Save and Continue


5. PAMS will return to the Products – Select Award Products page and display a green success message confirming that the Products list of the report was updated successfully. 

Image Added

Figure 17. Products – Select Award Products, Success


6. When you are finished selecting Products to add to the Award, click Save and Continue in the bottom right corner.

7. PAMS will return to the Progress Report – Products page and display a green success message confirming that the Products list of the report was updated successfully. 

Image Added

Figure 18. Progress Report – Products, Success

3.5.4

3. Once you have completed the Cover Page section, click Save and Continue in the bottom right corner of the page (Figure 6).

...

Image Removed

...

You can save your work without leaving the page at any time by clicking the Save button in the bottom right corner of the page, or leave the page without saving your progress by clicking the Go to Previous Section button in the bottom left corner.

4. PAMS will redirect you to the next section and display a Success message confirming that the Cover Page was saved successfully (Figure 7).

Image Removed

Figure 7. Cover Page Success Message

3.4 Completing the Accomplishments Section

The Accomplishments section of the progress report records the project’s performance over the duration of the award. This performance is tracked with a list of five questions pertaining to project goals, accomplishments, training and development opportunities, dissemination of results, and goals and intentions for the next reporting period. Use the following steps to complete the Accomplishments section of the progress report.

1. Navigate to the Accomplishments section by clicking Accomplishments in the left navigation menu, Update in the Options column on the Progress Report – Status page (Figure 5), or Save and Continue on the Cover Page (Figure 6).

2. PAMS will load the Progress Report – Accomplishments page (Figure 8). Fill in each textbox as appropriate. If applicable, you can select the “Nothing to Report” or “No Change” radio buttons and leave the accompanying textbox empty.

Image Removed

Figure 8. Progress Report – Accomplishments

...

Image Removed

...

  • You can attach one document in the Accomplishments Attachment section at the bottom of the page by clicking the Attach File button on the far right of the section header, browsing, and clicking Upload.
  • You can also include a description of 500 characters or less in the Accomplishments Attachment Description box. To edit the description or delete the attachment, click the Actions dropdown and select the appropriate action.

3. Once you have completed the required fields, select Save and Continue from the Choose Action dropdown and click Go (Figure 9).

Image Removed

Figure 9. Progress Report – Accomplishments – Choose Action

...

Image Removed

...

For any page with a Choose Action dropdown:

  • Select Save from the Choose Action dropdown to save your progress at any time without leaving the page.
  • Select Save and Continue from the Choose Action dropdown to save your work and continue on to the next section.
  • Select Mark as Complete from the Choose Action dropdown to mark the section as complete and continue on to the next section. All sections must be marked as complete before you can submit the progress report.
  • Click Go to Previous Section in the bottom left corner of the page to return to the previous section without saving your progress.

4. PAMS will load a Success message confirming that the Accomplishments section has been marked as complete successfully (Figure 10).

Image Removed

Figure 10. Progress Report – Accomplishments Success Message 

3.5 Completing the Products Section

The Products section of the progress report inventories all products created during the course of the project. There are four Product categories: Publications, Intellectual Property, Technologies or Techniques, and Other Products. Use the following steps to complete the Products section of the progress report.

1. Navigate to the products section by clicking Products in the left navigation menu, Update in the Options column on the Progress Report – Status page (Figure 5), or selecting Save and Continue from the dropdown menu on the Progress Report – Accomplishments page (Figure 9).

2. PAMS will load the Progress Report – Products page. Refer to the following sections for steps on how to add each applicable product type.

Image Removed

Figure 11. Progress Report – Products

...

Image Removed

...

Any products added to previous progress reports for this award or to the Products – List page between reports will display on this page. You do not need to add them again. For guidance on editing existing products, refer to section 3.5.5 Editing Existing Products. The Revision Type Column provides the status of each Product (“New” denotes a newly added Product, “Updated” denotes an existing Product that has been updated, and “No Change” denotes an existing Product with no changes in the Progress Report).

3.5.1 Adding a New Publication

There are seven types of Publications: Journal Article, Book, Book Chapter, Thesis/Dissertation, Conference Paper/Presentation, Website, and Other Publication. Use the following steps to add a Publication to your progress report.

1. Click the Add New Publication link under the Publications header on the Progress Report – Products page (Figure 11).

2. PAMS will load the Progress Report – Add New Publication page. Select a Publication type from the dropdown, and click Populate Form (Figure 12). PAMS will load a Publication type-specific form.

Image Removed

Figure 12. Progress Report – Add New Publication – Type

...

Image Removed

...

Click Save and Continue in the bottom right corner of the page after adding each item to save the item to the Publications section, or click Cancel in the bottom left corner of the page to cancel the item and return to the Progress Report – Products page.

3.5.1.1 Adding a New Publication – Journal Article

Refer to the table below to complete the required fields to add a Journal Article to your progress report.

Image Removed

Figure 13. Progress Report – Add New Publication – Journal Article

Required Fields

...

Element

...

Description

...

Type

...

This field contains the Publication type you selected and determines the Publication form you are filling out.

...

Article Title

...

Enter the title of the article.

...

Author(s)

...

Enter the name(s) of the author(s) of the article.

...

Journal

...

Enter the name of the journal in which the article is published or to be published.

...

Journal Peer Reviewed?

...

Select the “Yes” or “No” radio button to indicate whether the article was peer reviewed.

...

Publication Status

...

Click the dropdown and select one of the following to indicate the status of the publication: Published, Awaiting Publication, Accepted, Under Review, Submitted, or Other. If Other, specify in the box to the right of the dropdown.

...

Acknowledgement of DOE Support?

...

Select the “Yes” or “No” radio button to indicate whether an acknowledgement of DOE Support was provided to the publisher.

3.5.1.2 Adding a New Publication – Book

Refer to the table below to complete the required fields to add a Book to your progress report.

Image Removed

Figure 14. Progress Report – Add New Publication – Book

Required Fields

...

Element

...

Description

...

Type

...

This field contains the Publication type you selected and determines the Publication form you are filling out.

...

Book Title

...

Enter the title of the book.

...

Author(s)

...

Enter the name(s) of the author(s) of the book.

...

Publication Status

...

Click the dropdown and select one of the following to indicate the status of the publication: Published, Awaiting Publication, Accepted, Under Review, Submitted, or Other. If Other, specify in the box to the right of the dropdown.

...

Book Publisher

...

Enter the name of the book’s publisher.

...

Book Peer Reviewed?

...

Select the “Yes” or “No” radio button to indicate whether the book was peer reviewed.

...

Acknowledgement of DOE Support?

...

Select the “Yes” or “No” radio button to indicate whether an acknowledgement of DOE Support was provided to the publisher.

3.5.1.3 Adding a New Publication – Book Chapter

Refer to the table below to complete the required fields to add a Book Chapter to your progress report.

Image Removed

Figure 15. Progress Report – Add New Publication – Book Chapter

Required Fields

...

Element

...

Description

...

Type

...

This field contains the Publication type you selected and determines the Publication form you are filling out.

...

Chapter Title

...

Enter the title of the book chapter.

...

Author(s)

...

Enter the name(s) of the author(s) of the book chapter.

...

Book Title

...

Enter the title of the book.

...

Publication Status

...

Click the dropdown and select one of the following to indicate the status of the publication: Published, Awaiting Publication, Accepted, Under Review, Submitted, or Other. If Other, specify in the box to the right of the dropdown.

...

Book Publisher

...

Enter the name of the book’s publisher.

...

Chapter Peer Reviewed?

...

Select the “Yes” or “No” radio button to indicate whether the chapter was peer reviewed.

...

Acknowledgement of DOE Support?

...

Select the “Yes” or “No” radio button to indicate whether an acknowledgement of DOE Support was provided to the publisher.

3.5.1.4 Adding a New Publication – Thesis/Dissertation

Refer to the table below to complete the required fields to add a Thesis/Dissertation to your progress report.

Image Removed

Figure 16. Progress Report – Add New Publication – Thesis/Dissertation

Required Fields

Element

Description

Type

This field contains the Publication type you selected and determines the Publication form you are filling out.

Title

Enter the title of the thesis/dissertation.

Author(s)

Enter the name(s) of the author(s) of the thesis/dissertation.

Institution

Enter the name of the institution to which the thesis/dissertation was presented.

Acknowledgement of DOE Support?

Select the “Yes” or “No” radio button to indicate whether an acknowledgement of DOE Support was provided to the publisher.

3.5.1.5 Adding a New Publication – Conference Paper/Presentation

Refer to the table below to complete the required fields to add a Conference Paper/Presentation to your progress report.

Image Removed

Figure 17. Progress Report – Add New Publication – Conference Paper/Presentation

Required Fields

...

Element

...

Description

...

Type

...

This field contains the Publication type you selected and determines the Publication form you are filling out.

...

Paper Title

...

Enter the title of the conference paper/presentation.

...

Author(s)

...

Enter the name(s) of the author(s) of the conference paper/presentation.

...

Conference Name

...

Enter the name of the conference for which the conference paper/presentation was written.

...

Conference Location

...

Enter the city and country in which the conference was held.

...

Conference Date

...

Enter the date on which the conference began.

...

Publication Status

...

Click the dropdown and select one of the following to indicate the status of the publication: Published, Awaiting Publication, Accepted, Under Review, Submitted, or Other. If Other, specify in the box to the right of the dropdown.

...

Acknowledgement of DOE Support?

...

Select the “Yes” or “No” radio button to indicate whether an acknowledgement of DOE Support was provided to the publisher.

3.5.1.6 Adding a New Publication – Website

Refer to the table below to complete the required fields to add a website to your progress report.

Image Removed

Figure 18. Progress Report – Add New Publication – Website

Required Fields

Element

Description

Type

This field contains the Publication type you selected and determines the Publication form you are filling out.

Title

Enter the title of the website.

URL

Enter the web address.

3.5.1.7 Adding a New Publication – Other Publication

Refer to the table below to complete the required fields to add an Other Publication to your progress report.

Image Removed

Figure 19. Progress Report – Add New Publication – Other Publication

Required Fields

...

Element

...

Description

...

Type

...

This field contains the Publication type you selected and determines the Publication form you are filling out.

...

Title

...

Enter the name of the publication.

...

Author(s)

...

Enter the name(s) of the author(s) of the publication.

...

Description

...

Enter a description of the publication.

...

Publication Status

...

Click the dropdown and select one of the following to indicate the status of the publication: Published, Awaiting Publication, Accepted, Under Review, Submitted, or Other. If Other, specify in the box to the right of the dropdown.

...

Acknowledgement of DOE Support?

...

Select the “Yes” or “No” radio button to indicate whether an acknowledgement of DOE Support was provided to the publisher.

3.5.2 Adding a New Intellectual Property

There are three types of Intellectual Property: Patent, Invention, and License. Use the following steps to add an Intellectual Property to your progress report.

1. Click the Add New Intellectual Property link under the Intellectual Property header on the Progress Report – Products page (Figure 11).

2. PAMS will load the Progress Report – Add New Intellectual Property page. Select an Intellectual Property type from the dropdown, and click Populate Form (Figure 20). PAMS will load an Intellectual Property type-specific form.

Image Removed

Figure 20. Progress Report – Add New Intellectual Property

...

Image Removed

...

Click Save and Continue in the bottom right corner of the page after adding each item to save the item to the Publications section, or click Cancel in the bottom left corner of the page to cancel the item and return to the Progress Report – Products page.

3.5.21 Adding a New Intellectual Property – Patent

Refer to the table below to complete the required fields to add a Patent to your progress report.

Image Removed

Figure 21. Progress Report – Add New Intellectual Property – Patent

Required Fields

...

Element

...

Description

...

Type

...

This field contains the Publication type you selected and determines the Publication form you are filling out.

...

Patent Title

...

Enter the name of the patent.

...

Patent Abstract

...

Enter an abstract describing the patent.

...

Patent Number

...

Enter the number of the patent.

...

Country

...

Use the dropdown to select the country in which the patent resides.

...

Applicable Status

...

Use the dropdown to select one of the following to describe the status of the patent application: Submitted, Pending, or Granted.

3.5.2.2 Adding a New Intellectual Property – Invention

Refer to the table below to complete the required fields to add an Invention to your progress report.

Image Removed

Figure 22. Progress Report – Add New Intellectual Property – Invention

Required Fields

Element

Description

Type

This field contains the Publication type you selected and determines the Publication form you are filling out.

Invention Title

Enter the name of the invention.

Inventors

Enter the name(s) of the inventor(s).

Invention Description

Enter a description of the invention.

3.5.2.3 Adding a New Intellectual Property – License

Refer to the table below to complete the required fields to add a License to your progress report.

Image Removed

Figure 23. Progress Report – Add new Intellectual Property – License

Required Fields

...

Element

...

Description

...

Type

...

This field contains the Publication type you selected and determines the Publication form you are filling out.

...

License Title

...

Enter the name of the license.

...

License Status

...

Use the dropdown to select one of the following to describe the status of the license: None, Pending, or Licensed.

3.5.3 Adding a New Technology or Technique

There is only one type of Technology or Technique. Use the following steps to add a Technology or Technique to your progress report.

1. Click the Add New Technology or Technique link under the Technologies or Techniques header on the Progress Report – Products page (Figure 11).

2. PAMS will load the Progress Report – Add New Technology or Technique page (Figure 24). Refer to the table below to complete the required fields to add a technology or technique to your progress report.

Image Removed

Figure 24. Progress Report – Add New Technology or Technique

Required Fields

...

Element

...

Description

...

Description

...

Enter the name and a description of the technology or technique produced.

3.5.4 Adding an Other Product

All products that do not fall into any of the previous categories are recorded under Other Product. These products include: Audio or Video, Databases, Data and Research Material, Education Aids or Curricula, Evaluation Instruments, Instruments or Equipment, Models, Physical Collections, Protocols, Software or NetWare, Survey Instruments, and Other. Use the following steps to add an Other Product to your progress report.

1. Click the Add Other Product link under the Other Products header on the Progress Report – Products page (Figure 11).

2. PAMS will load the Progress Report – Add Other Product page (Figure 25). Refer to the table below to complete the required fields to add an Other Product to your progress report.

Image Removed

Figure 25. Progress Report – Add Other Product

Required Fields

...

Element

...

Description

...

Product Type

...

Use the dropdown to select one of the following to describe the product type: Audio or Video, Databases, Data and Research Material, Education Aids or Curricula, Evaluation Instruments, Instruments or Equipment, Models, Physical Collections, Protocols, Software or NetWare, Survey Instrument, or Other. If Other, specify in the box to the right of the dropdown.

...

Description

...

Enter a description of the product and how it is being shared.

3.5.5 Editing Existing Products

Use the following steps to make any changes to a product in the Products section.

3.5.5.1 Updating an Existing Product

1. Navigate to the Progress Report – Products page by clicking Products in the left navigation menu, Update in the Options column on the Progress Report – Status page (Figure 5), or selecting Save and Continue from the dropdown menu on the Progress Report – Accomplishments page (Figure 9).

2. Click Update in the Actions/Views dropdown for the product you would like to update. PAMS will redirect you to the product’s page (refer to the Product pages above).

3. Click Save and Continue to save any changes when you are finished, or click Cancel to cancel any changes.

3.5.5.2 Deleting an Existing Product

1. Navigate to the Progress Report – Products page by clicking Products in the left navigation menu, Update in the Options column on the Progress Report – Status page (Figure 5), or selecting Save and Continue from the dropdown menu on the Progress Report – Accomplishments page (Figure 9).

2. Click Delete in the Action/Views dropdown for the product you would like to delete (Figure 11).

3. PAMS will display a Confirmation message asking if you are sure you want to delete the product (Figure 26). Read the message carefully. If you are sure you want to delete the product, click Confirm. If you do not want to delete the product, click Cancel.

Image Removed

Figure 26. Progress Report – Products – Delete Product Confirmation Message

4. PAMS will load a Success message confirming that the product was deleted successfully (Figure 27).

Image Removed

Figure 27. Progress Report – Products – Delete Product Success Message

...

Marking the Products Section as Complete

Use the following steps to mark the Products section of the progress report as complete.

1. Once you have completed the Products section, click Mark as Complete in the bottom right corner of the page (Figure 11).

...

...

You can view a product at any time before submitting the progress report by clicking the Actions/Views dropdown on the Progress Report – Products page and selecting View. The product will load in a popup window on top of the main window. Click the Close Window button in the bottom right corner when you are finished.

2. PAMS will redirect you to the next section and display a Success message confirming that the Products page was marked as complete successfully (Figure 28).

Figure 2819. Progress Report – Products – Success Message

...

1. Navigate to the Participants section by clicking Participants in the left navigation menu, Update in the Options column on the Progress Report – Status page (Figure 5), or Save and Continue on the Progress Report – Products page (Figure 11).

2. PAMS will load the Progress Report – Participants page (Figure 29). Refer to the following sections for steps on how to add each applicable Participant type.

Image RemovedImage Added

Figure 2920. Progress Report – Participants

...

1. Click the Add New Participant link under the Participants header on the Progress Report – Participants page (Figure 29).

2. PAMS will load the Progress Report – Add New Participant – List page (Figure 30). Use the Last Name like, First Name Like, and Email like fields to search for the registered PAMS user(s) you would like to add to the progress report. Click Search to see the list of results.

Image AddedImage Removed
Figure 3021. Progress Report – Add New Participant – List

3. Browse the list. When you have found the user you would like to add, click Add Participant in the Options column (Figure 31).

Image RemovedImage Added

Figure 3122. Progress Report – Add New Participant – List, Add Participant

  • Only users who are register to the institution will appear in the search results.
  • Users who are already listed as Participants on the progress report will have an “Already Added” read-only label in the Options column. You cannot add these users again, but you can edit their project information from the Participants section.
  • If the person you wish to add as a participant does not appear in the list of search results on the Progress Report – Add New Participant – List page, click the Add New Participant link above the search results grid (Figure 31). PAMS will direct you to the Progress Report – Add New Participant page shown above (Figure 32); however, the First Name and Last Name fields will be empty. Enter the names of the participant, and complete the remaining required fields.

4. PAMS will load the Progress Report – Add New Participant page (Figure 32). Refer to the table below to complete the required fields to add a new participant to the progress report.

...

Element

Description

First Name

The first name of the person you are reporting as a participant will already be entered. You will not be able to edit this field.

Last Name

The last name of the person you are reporting as a participant will already be entered. You will not be able to edit this field.

Project Role

Use the dropdown to select the role the participant filled on the project. If Other, specify the project role in the box to the right of the dropdown.

Person Months Worked

Enter the number of months the person worked on the project. Round the number to the nearest whole number.

Contribution to the Project

Enter a description of the person’s contribution to the project.

International Collaboration?

Select the “Yes” or “No” radio button to indicate whether the participant collaborated with any individuals in a foreign country as a part of this project during the reporting period.

If “Yes”, click the Add New Country link above the Country header, and use the dropdown to select the country of the international collaborator.

International Travel?

Select the “Yes” or “No” radio button to indicate whether the participant travelled to a foreign country as a part of this project during the reporting period.

If “Yes”, click the Add New Country link above the Country header, and use the dropdown to select the country to which the participant travelled.

Image RemovedImage Added

Figure 3223. Progress Report – Add New Participant

5. Once you have completed the page, select Mark as Complete from the Choose Action dropdown and click Go to save your work and return to the Progress Report – Participants page (Figure 33).

Image Modified

Figure 3324. Progress Report – Add New Participant – Choose Action

...

1. Click the Add New Partner link under the Partners header on the Progress Report – Participants page (Figure 29).

2. PAMS will load the Progress Report – Add New Partner page (Figure 34). Refer to the table below to complete the required fields to add a new partner to the progress report.

Image RemovedImage Added

Figure 3425. Progress Report – Add New Partner

...

1. Click the Add Other Collaborator link under the Other Collaborators header on the Progress Report – Participants page (Figure 29).

2. PAMS will load the Progress Report – Add Other Collaborator page (Figure 35). Refer to the table below to complete the required fields to add an Other Collaborator to the progress report.

Image RemovedImage Added

Figure 3526. Progress Report – Add Other Collaborator

...

1. Navigate to the Progress Report – Participants page by clicking Participants in the left navigation menu, Update in the Options column on the Progress Report – Status page (Figure 5), or Mark as Complete on the Progress Report – Products page (Figure 11).

2. Click Update in the Actions/Views dropdown for the participant you would like to update (Figure 29). PAMS will redirect you to the participant’s page (refer to the Participant pages above).

...

1. Navigate to the Progress Report – Participants page by clicking Participants in the left navigation menu, Update in the Options column on the Progress Report – Status page (Figure 5), or Mark as Complete on the Progress Report – Products page (Figure 11).

2. Click Delete in the Action/Views dropdown for the participant you would like to delete (Figure 29).

3. PAMS will display a Confirmation message asking if you are sure you want to delete the participant (Figure 36). Read the message carefully. If you are sure you want to delete the participant, click Confirm. If you do not want to delete the participant, click Cancel.

Figure 3627. Progress Report – Participant – Delete Participant Confirmation Message

4. PAMS will load a Success message confirming that the participant was deleted successfully (Figure 37).

Figure 3728. Progress Report – Participant – Delete Participant Success Message

...

1. Once you have completed the Participants section, click Mark as Complete in the bottom right corner of the page (Figure 29).

2. PAMS will redirect you to the next section and display a Success message confirming that the Products page was marked as complete successfully (Figure 38).

Figure 3829. Progress Report – Participant Success Message

...

The Impact section of the progress report enables you to describe the impact of the project and to report spending in foreign countries. Impact is tracked with a list of five seven questions pertaining to the development of the project’s principal disciplines, other disciplines, human resources, resources that form infrastructure, technology transfer, and society as a whole. Use the following steps to complete the Impact section of the progress report.

1. Navigate to the Impact section by clicking Impact in the left navigation menu, Update in the Options column on the Progress Report – Status page (Figure 5), or Mark as Complete on the Progress Report – Participants page (Figure 29).

2. PAMS will load the Progress Report – Impact page (Figure 39). Fill in each textbox as appropriate.

Textboxes that are left blank are marked as “Nothing to Report”.

Image RemovedImage Added

Figure 3930. Progress Report – Impact

...

1. Click Add New Foreign Spending above the Foreign Spending header on the Progress Report – Impact page (Figure 40).

Figure 4031. Progress Report – Impact – Foreign Spending

2. PAMS will add an empty row to the Foreign Spending section. Click the Country dropdown to select the country in which the funds were spent (Figure 41).

3. Enter the dollar amount of the award’s funds spent in the foreign country.

Figure 4132. Progress Report – Impact – Foreign Spending, Information

...

1. Once you have completed the Impact section, select Mark as Complete from the Choose Action dropdown and click Go (Figure 42).

Image Modified

Figure 4233. Progress Report – Impact – Choose Action

2. PAMS will redirect you to the next section and display a Success message confirming that the Products page was marked as complete successfully (Figure 43).

Figure 4334. Progress Report – Impact – Success Message

...

1. Navigate to the Changes-Problems section by clicking Changes-Problems in the left navigation menu, Update in the Options column on the Progress Report – Status page (Figure 5), or by selecting Mark as Complete on the Progress Reports – Impact page (Figure 42).

2. PAMS will load the Progress Report – Changes-Problems page (Figure 44). Fill in each textbox as appropriate.

  • Textboxes that are left blank are marked as “Nothing to Report”.
  • The Carryover Amount section is required and cannot be left blank.

Image RemovedImage Added

Figure 4435. Progress Report – Changes-Problems


Image Added

For Lab Awards, the field under section "6. Carryover Amount" will read as follows: "Projected uncosted project balance for current scope of work at reporting period end."


3. Once you have completed the Changes-Impact section, select Mark as Complete from the Choose Action dropdown in the bottom right corner of the page and click Go (Figure 45).

Image Modified

Figure 4536. Progress Report – Changes-Problems – Choose Action

4. PAMS will redirect you to the next section and display a Success message confirming that the Changes-Problems page was marked as complete successfully (Figure 46).

Figure 4637. Progress Report – Changes-Problems Success Message

3.9 Completing the

...

Participant Information for Significant Contributors Section

This page displays the significant contributors entered in the Participants section of the Progress Report – Participants page. To complete this page, email addresses must be provided for all contributors. Use the following steps to complete the Demographic Participant Information for Significant Contributors section of the progress report.

1. Navigate to the Demographic Participant Information for Significant Contributors section by clicking Demographic Information Participant Information in the left navigation menu, Update in the Options column on the Progress Report – Status page (Figure 5), or by selecting Mark as Complete on the Progress Reports – Changes-Problems page (Figure 45).

2. PAMS will load the Progress Report – Demographic Participant Information for Significant Contributors page. Ensure that each user has an email address listed. If an email address is missing, click Update in the Actions/Views dropdown in the Options column (Figure 47).

  • You will not be able to update the email address for registered users. Upon submission of the progress report, PAMS will send an automatic email to the contributors you listed who are not registered in PAMS, inviting them to register.
  • You can view a contributor’s information by selecting View in the Actions/Views dropdown on the Progress Report – Demographic Participant Information for Significant Contributors page. The information will load in a popup window on top of the main window. Click the Close Window button in the bottom right corner when you are finished.

Image RemovedImage Added

Figure 4738. Progress Report – Demographic Participant Information for Significant Contributors

3. PAMS will load the Progress Report – Update Demographic Participant Information for Significant Contributors page (Figure 48)page. Enter the user’s email address.

Image RemovedImage Added

Figure 4839. Progress Report – Update Demographic Participant Information for Significant Contributors

4. When you are finished, click Save and Continue in the bottom right corner of the page to save your changes, or click Cancel in the bottom left corner to return to the Progress Report – Demographic Participant Information for Significant Contributors page without saving any changes.

5. PAMS will display a Success message confirming that the information was saved successfully (Figure 49).

Image RemovedImage Added

Figure 4940. Progress Report – Update Demographic Participant Information for Significant Contributors Success Message

6. Once you have completed the Demographic Participant Information for Significant Contributors section, click Mark as Complete in the bottom right corner of the page (Figure 47).

7. PAMS will redirect you to the next section and display a Success message confirming that the Demographic Participant Information for Significant Contributors page was marked as complete successfully (Figure 50).

Image RemovedImage Added

Figure 5041. Progress Report – Demographic Participant Information for Significant Other Success Message

...

1. Navigate to the Attachments section by clicking Attachments in the left navigation menu, Update in the Options column on the Progress Report – Status page (Figure 5), or Mark as Complete on the Progress Reports – Demographic Participant Information for Significant Contributors page (Figure 47).

2. PAMS will load the Progress Report – Attachments page. To add attachments, click Attach File in the Special Reporting Requirements header (Figure 51).

Image Removed

...

.

Image Added

Figure 42. Progress Report – Attachments


Image Added

For Lab Awards, the Note will read as follows: "Progress Reports may only contain attachments if required by DOE. Attachments that are not required will not be disregarded."


3. Click Browse, and select the files you would like to attach to the progress report (Figure 51).

  • You can attach a maximum of three (3) attachments.
  • You can include a description of 500 characters or less for the attachments in the Description box in the Special Reporting Requirements section.

4. Once you have selected the files you would like to attach, click Upload (Figure 51).

To edit the Attachment Description or delete the attachment, click the Actions dropdown in the Options column and select the appropriate action.

5. Once you have completed the Progress Report – Attachments page, or if you are skipping this page, click Mark as Complete in the bottom right corner of the page (Figure 51).

6. PAMS will redirect you to the next section and display a Success message confirming that the Progress Report – Attachments page was marked as complete successfully (Figure 52).

Figure 5243. Progress Report – Attachments Success Message

...

1. Select Update Description in the Actions menu in the Options column (Figure 53).

Figure 5344. Progress Report – Attachments – Update Description

2. Click Save when you are finished to save any changes, or click Cancel to cancel any changes (Figure 54).

Figure 5445. Progress Report – Attachments – Update Description Save/Cancel

...

1. Select Delete in the Actions menu in the Options column (Figure 55).

Figure 5546. Progress Report – Attachments – Delete

2. PAMS will display a Confirmation message asking if you are sure you want to delete the attachment (Figure 56). If you are sure you want to delete the attachment, click click Confirm. If you do not want to delete the attachment, click Cancel. PAMS will reload the Progress Report – Attachments page, and the attachment will no longer display in the Special Reporting Requirements section.

Figure 5647. Progress Report – Attachments – Delete Attachment Confirmation Message

...

1. Navigate to the Review page by clicking Review in the left navigation menu (Figure 5). PAMS will load the Progress Report – Review page, which displays a summary of the progress report’s eight sections (Figure 57).

2. To review a section, click View in the Views dropdown menu in the Options column.

Image RemovedImage Added

Figure 5748. Progress Report – Review, View

...

4. If you would like to return to a previous section and make updates, click the section’s link in the left navigation menu (Figure 57). (Refer to the appropriate module above for guidance on completing each section of the progress report.)

5. When you are finished reviewing the progress report on the Progress Report – Review page, click the Continue button in the bottom right corner of the page (Figure 57).

4.2 Submitting a Progress Report

...

1. Navigate to the submission page by clicking Continue on the Progress Report – Review page, or Submit in the left navigation menu (Figure 57).

2. PAMS will load the Progress Report – Submit page, which displays a summary of the progress report sections with their completion status (Figure 58). Each section should display “Complete” with a green checkmark in the status column. If a section is incomplete (marked as “In Progress” or “Not Started” with a green checkmark with a red slash), click the Update button for the section. (Refer to the appropriate module above for guidance on completing the section successfully.)

3. Click the Preview Public Progress Report PDF button or Preview DOE Progress Report buttons in the bottom right corner of the page to preview the public and DOE versions of the progress report before submitting (Figure 58). This is your last opportunity to review the progress report before submitting it to DOE.

Image RemovedImage Added

Figure 5849. Progress Report – Submit

...

5. If you would like to edit a section, click Update in the Options column for that section. If you are ready to submit the progress report, click Submit in the bottom right corner of the page. (Figure 58) in the Options column for that section. If you are ready to submit the progress report, click Submit in the bottom right corner of the page.

Image Added

If you have the Submit to DOE privilege, PAMS will provide a Submit button at the bottom of the page. Clicking the Submit button will submit the Progress Report to DOE Office of Science, and you will no longer be able to edit the Progress Report.

If you do not have the Submit to DOE privilege, PAMS will provide a Submit for Countersignature button. Clicking the Submit for Countersignature button will submit the Progress Report to your Institution's countersigner(s), and you will no longer be able to edit the Progress Report

Image Removed

Clicking Submit will submit the progress report to DOE. You will not be able to make any changes to the progress report once it has been submitted.

6. PAMS will redirect you to the Progress Report – List page and display a Success message confirming that the progress report was submitted successfully (Figure 59).

Figure 5950. Progress Report – List, Success Message