The chart below is meant to provide a guideline for the completion of the many steps involved in an SBIR/STTR grant application. Certain steps will take much longer than others, while others will require more leg work to complete such as gathering required documentation from collaborating partners and securing biosketches from key personnel who may not be employed by the applicant organization. Further, it is essential that applicants allow themselves as much time as possible to work on the Project Narrative and provide an application that is responsive to the FOA.
This schedule was developed with small business organizations in mind that have limited staff and are relatively new to the SBIR/STTR grant application process. We recognized that experienced grant writers or companies with larger staffs, and personnel dedicated to specific areas, may approach this process differently.
| 8 week schedule - starts when Funding Opportunity Released |
| 1 (8/7) | 2 | 3 8/21 | 4 (8/28) | 5 | 6 | 7 | 8 | 9 | 10 (10/9) |
Download / review FOA | Select FOA |
|
|
|
|
|
|
|
|
|
Decide SBIR/STTR | SBIR or STTR |
|
|
|
|
|
|
|
|
|
Contact Topic Author |
| Send email | Follow-up |
|
|
|
|
|
|
|
Locate Service Providers | SBDC, PTAC, Phase 0 |
|
|
|
|
|
|
|
|
Registrations | PAMS | SAM Registration |
| Grants.gov | SBA |
|
|
|
|
Prepare Project Narrative |
| Write part | Get feedback | Write more | Get feedback | Write more | Get Feedback | Tweak & add markings | Finalize |
|
Letter of Intent (LOI) |
| Draft | Get Feedback | Submit LOI |
|
|
|
|
|
|
Principal Investigator (PI) role |
|
|
| Role? | Confirm who |
|
|
|
|
|
Budget |
|
| Think about | Start preparing | Keep working | Get Feedback | Finalize |
|
|
Budget Justification |
|
|
|
| Staffing $ | Facilities $ | Get Feedback | Finalize |
|
|
Employees, subs, consultants |
|
|
|
| Discuss | Confirm |
|
|
|
|
Required Forms (RI, subs) |
|
|
|
| Distribute | Follow-up | Secure |
|
|
|
NEW ITEM: PIER PLAN |
|
|
|
| Think about | Reach out | Prepare |
|
|
|
Commercialization Plan |
|
|
| Review Example | Draft | Get Feedback | Finalize |
|
|
|
Letters of Support |
|
|
| Think about | Reach out | Follow up | Secure |
|
|
|
Access Grants.gov workspace |
|
|
|
| Download forms & start completing | Get feedback as needed | Finalize |
|
|
|
Prepare Abstract/Summary |
|
|
|
|
| Prepare |
|
|
|
|
Biosketches |
|
|
| Format | Request all | Proof |
|
|
|
|
Full Application due |
|
|
|
|
|
|
|
| Submit early? | Application due - Monday |
Have questions about FOA? | Reach out to DOE Help Desk as needed; as well as help for Grants.gov and PAMS |
Week | Activities - 8 Week Calendar |
1 | FOA Released - Locate appropriate FOA in grants.gov, download, and review for application requirements & specifics
- Determine type of application: SBIR, STTR, or Both
- Download & review topics/subtopics document
- Determine potential topic/subtopic pair
- Research issuing office - review mission, needs, research, programs
- Assess ability to successfully respond to topic/subtopic pair
- Contact Topic Author/Manager if you have questions
- Consider personnel and/or partnerships required to respond to topic/subtopic pair
- Begin drafting LOI
- Download DOE SBIR/STTTR application checklist
- Begin SAM registration and PAMS registration
|
2 | - If STTR application, or working with RI, consortia, or any partnering organizations, begin contacting those organization if known. If you do not have established contacts, review partnering resources.
- Determine PI and Key/Senior Persons
- Begin drafting Project Narrative
- Review PIER Plan requirements and begin formulating PIER Plan
- Review Commercialization Plan requirements and determine if outside assistance from service provider needed
|
3 | - Register in Grants.gov
- Request letters of commitment/funding/support from RI, consortia, and/or any partnering organizations
- Finalize senior / key personnel and begin completing biosketches
- Begin completing Current & Pending Support for PI and key / senior persons
- Continue drafting Project Narrative
- Continue to formulate budget
- If working with a service provider or reviewer, begin providing Project Narrative sections for review as they are completed for comments
|
4 | LOI due - Submit LOI in PAMS
- Begin entering information on the SF424 webform in Grants.gov
- Finalize biosketches for PI and all senior/key persons
- Continue drafting Project Narrative
- Continue to formulate budget
- Divide time between creative aspects of writing Project Narrative and completing required forms - R & R Senior/Key Person Form, R&R Other Project Information Form, SBIR/STTR Information Form.
|
5 | - If partnering with RI or any subcontractors, send subaward budget documents (downloaded from grants.gov application workspace) to RI or representative for completion
- Continue drafting Project Narrative
- Continue to formulate budget
- Begin Budget Justification Form
- Determine data management plan; if working with an RI, ensure that there is agreement on how/if data is to be shared
|
6 | - Verify SAM registration complete
- Register as SBC on SBIR.gov
- Continue drafting Project Narrative
- Continue to formulate budget
- Divide time between creative aspects of writing Project Narrative and completing required forms - R & R Senior/Key Person Form, R&R Other Project Information Form, SBIR/STTR Information Form.
- Complete Level of Effort and Max Funding spreadsheet
- Review DOE application checklist to ensure all required forms have been completed
|
7 | Non-responsive feedback, if any, issue - If you receive non-responsive feedback, review, address the comments, and determine next steps
- Begin finalizing Project Narrative
- Begin finalizing Budget
- Review subaward budgets (if any) from RI and/or subcontractors
- Finalize PIER Plan
- Finalize Commercialization Plan
- Finalize Budget Justification Form
|
8 | - Review Project Narrative for necessary edits and/or adjustments
- Review Budget for any errors or inconsistencies
- Review Budget Justification to ensure consistency with Budget
- Review DOE checklist to ensure all necessary forms completed
|
9 | Submit application |