The chart below is meant to provide a guideline for the completion of the many steps involved in an SBIR/STTR grant application. This planner begins with the release of the FOA. Certain steps will take much longer than others, while others will require more leg work to complete such as gathering required documentation from collaborating partners and securing biosketches from key personnel who may not be employed by the applicant organization. Further, it is essential that applicants allow themselves as much time as possible to work on the Project Narrative and provide an application that is responsive to the FOA.
This schedule was developed with small business organizations in mind that have limited staff and are relatively new to the SBIR/STTR grant application process. We recognized that experienced grant writers or companies with larger staffs, and personnel dedicated to specific areas, may approach this process differently. In addition to the actions listed below, applicants should also review the DOE Funding Opportunities website and plan to attend upcoming webinars associated with the FOA.
Accelerated schedule - starts when Funding Opportunity Released | ||||||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | |
Download / review FOA | Download FOA | |||||||||
Decide SBIR/STTR/Both | SBIR, STTR, or Both | If STTR, reach out to Research Institution (RI) | ||||||||
Contact Topic Author | Contact Topic Author | Follow up (if necessary) | ||||||||
Locate Service Providers | Visit https://www.sbir.gov/local-assistance | |||||||||
Registrations | PAMS | SBA | Grants.gov | |||||||
SAM | ||||||||||
Prepare Project Narrative | Gather & Adjudicate Feedback on Outline | Complete Draft of First Half* | Gather & Adjudicate Feedback on First Half | Complete Draft of Second Half** | Gather & Adjudicate Feedback on Second Half | Add Proprietary Markings | Finalize | |||
Letter of Intent (LOI) | Write Draft LOI | Gather & Adjudicate Feedback | Submit LOI | |||||||
Principal Investigator (PI) role | Determine Possible PI's | Define and document PI's role on the project | Confirm final PI | Author PI Biosketch, and Current/Pending Support List (C/PSL) | ||||||
Budget | Determine Project Scope | Create Budget Estimate | Detailed Budget Assembly | Gather & Adjudicate Feedback (if necessary) | Finalize | |||||
Employees, subs, consultants | Estimate Staffing Needs | Build Staff Breakdown (Employee/Sub/1099) | Gather & Adjudicate Feedback (if necessary) | Confirm | ||||||
Commercialization Plan | Review Examples and Create outline | Create First Draft | Gather & Adjudicate Feedback (if necessary) | Finalize | ||||||
Letters of Support | Create a list of possible references | Contact References & Provide Guidance | Follow Up & Finalize Letters of Support | Finalize Letters of Support | ||||||
Access Grants.gov workspace | Log-In & Begin Completing Forms | Complete Forms as Required by your FOA | Finalize Forms as Required by your FOA | |||||||
Prepare Abstract/Summary | Author Abstract | |||||||||
Biosketches & Current / Pending Support List (C/PSL) | Identify Personnel | Request Biosketches from all Personnel | Review, provide feedback, and ask for updates | Finalize all Biosketches and (C/PSL) | ||||||
Full Application due | Submit early? | Application due - Monday | ||||||||
Have questions about FOA? | Reach out to DOE Help Desk as needed; as well as help for Grants.gov and PAMS |
Week | Activities - Accelerated Calendar |
1 | FOA Released
|
2 |
|
3 |
|
4 | LOI due
|
5 |
|
6 |
|
7 | Non-responsive feedback, if any, issue
|
8 |
|
9 | Final review of application package and submit application. |