The chart below is meant to provide a guideline for the completion of the many steps involved in an SBIR/STTR grant application. This planner begins with the release of the FOA. Certain steps will take much longer than others, while others will require more leg work to complete such as gathering required documentation from collaborating partners and securing biosketches from key personnel who may not be employed by the applicant organization. Further, it is essential that applicants allow themselves as much time as possible to work on the Project Narrative and provide an application that is responsive to the FOA.
This schedule was developed with small business organizations in mind that have limited staff and are relatively new to the SBIR/STTR grant application process. We recognized that experienced grant writers or companies with larger staffs, and personnel dedicated to specific areas, may approach this process differently. In addition to the actions listed below, applicants should also review the DOE Funding Opportunities website and plan to attend upcoming webinars associated with the FOA.
8 week schedule Accelerated schedule - starts when Funding Opportunity Released |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 |
Download / review FOA |
Select STTRBoth | If STTR, reach out to Research Institution (RI) |
|
|
|
|
|
|
|
|
Contact Topic Author |
Send emailContact Topic Author | Follow |
- up (if necessary) |
|
|
|
|
|
|
|
|
Locate Service Providers |
SBDC, PTAC, Phase 0SAM RegistrationSBA
|
|
|
|
SAM |
|
|
|
|
|
|
|
|
Prepare Project Narrative |
Write part | Get feedback | Write more | Get feedback | Write more | Get Feedback | Tweak & add markings
|
| Gather & Adjudicate Feedback on Outline | Complete Draft of First Half* | Gather & Adjudicate Feedback on First Half | Complete Draft of Second Half** | Gather & Adjudicate Feedback on Second Half | Add Proprietary Markings | Finalize |
|
Letter of Intent (LOI) |
| Write Draft LOI |
Get Gather & Adjudicate Feedback | Submit LOI |
|
|
|
|
|
|
Principal Investigator (PI) role |
Think about | Role? | Confirm who | Complete biosketch & current & pending funding |
|
| Determine Possible PI's | Define and document PI's role on the project | Confirm final PI | Author PI Biosketch, and Current/Pending Support List (C/PSL) |
|
|
|
|
Budget |
|
| Determine Project Scope | Create Budget Estimate | Detailed Budget Assembly | Gather & Adjudicate Feedback (if necessary) |
Budget | Think about | Start preparing | Keep working | Get Feedback | Finalize | Budget Justification | Staffing $ | Facilities $ | Get Feedback | Finalize |
|
|
|
Employees, subs, consultants |
Discuss | Discuss | Discuss | Confirm | Required Forms (RI, subs) | Distribute | Follow-up | Secure | NEW ITEM: PIER PLAN | Think about | Reach out |
|
|
| Estimate Staffing Needs | Build Staff Breakdown (Employee/Sub/1099) | Gather & Adjudicate Feedback (if necessary) | Confirm |
Prepare |
|
|
|
Commercialization Plan |
|
|
| Review |
ExampleExamples and Create outline | Create First Draft |
Get FeedbackGather & Adjudicate Feedback (if necessary) | Finalize |
|
|
|
Letters of Support |
Think about | Reach out | Follow up |
|
|
| Create a list of possible references | Contact References & Provide Guidance | Follow Up & Finalize Letters of Support | Finalize Letters of Support |
SecureDownload forms & start completing | Get feedback as needed |
|
|
|
| Log-In & Begin Completing Forms | Complete Forms as Required by your FOA | Finalize Forms as Required by your FOA |
FinalizePrepare
|
|
|
|
| Author Abstract |
|
|
|
|
Biosketches & Current / Pending Support |
FormatList (C/PSL) |
|
|
| Identify Personnel | Request Biosketches from all |
Proof | ProofPersonnel | Review, provide feedback, and ask for updates | Finalize all Biosketches and (C/PSL) |
|
|
|
Full Application due |
|
|
|
|
|
|
|
| Submit early? | Application due - Monday |
Have questions about FOA? | Reach out to DOE Help Desk as needed; as well as help for Grants.gov and PAMS |
Week | Activities - 8 Week CalendarAccelerated Calendar |
1 | FOA Released - Locate appropriate FOA in grants.gov, download, and review for application requirements & specifics
- Determine type of application: SBIR, STTR, or Both.
- Research issuing office - review mission, needs, research, programs.
- Assess ability to successfully respond to FOA.
- Begin PAMS registration.
- Visit the Find Local Assistance page at SBIR.gov to locate service providers, such as Small Business Development Centers (SBDC), Procurement Technical Assistance Centers (PTACs), many othersLocate service providers - SBDC, PTAC, etc.
- Contact Topic Author/Manager if you have questions.
- Download DOE SBIR/STTTR application checklist.
|
2 | - If STTR application, or working with RI, consortia, or any partnering organizations, begin contacting those organization if known. If you do not have established contacts, review partnering resources.
- Continue contacts with service providers if necessary.
- Draft LOI
- Begin SAM registration
- Begin drafting Document and finalize Project Narrative outline.
|
3 | - Continue working on SAM registration
- If working with an external reviewer, submit narrative elements completed thus far and seek feedbackgather and adjudicate feedback on Project Narrative outline.
- If working with an external reviewer, submit LOI draft gather and seek adjudicate feedback
- Begin thinking about, and formulating, the budget if possible
- Request letters of commitment/funding/support from RI, consortia, and/or any partnering organization
- Consider personnel and/or partnerships required to respond
- Begin considering PI and the role they will take in the project
- Continue drafting Project Narrative
- Continue to formulate budget
- on LOI.
- Determine possible PIs.
- Determine project scope for budgeting purposes.If working with a service provider or reviewer, begin providing Project Narrative sections for review as they are completed for comments
|
4 | LOI due - Submit LOI in PAMS
- Continue considering personnel and/or partnerships required to respond
- Review and download commercialization plan
- Continue drafting Project Narrative
- Continue to formulate budget
- Begin to format biosketches & current / pending support
- Divide time between creative aspects of writing Project Narrative and completing required forms - R & R Senior/Key Person Form, R&R Other Project Information Form, SBIR/STTR Information Form.
- Complete draft of first half of Project Narrative. *Please note, "first half" equates to the following Narrative elements: Identification of the Problem & Technical Approach, Anticipated Public Benefits, Technical Objectives & Work Plan, and the Performance Schedule.
- Define and document PI's role on the project.
- Create budget estimate.
- Estimate staffing needs.
- Review example Commercialization Plan and create outline.
- Create list of potential references to supply Letters of Support.
- Identify personnel for which biosketches and/or current & pending support information is required.Consider/determine necessary letters of commitment/funding/support from RI, consortia, and/or any partnering organization
|
5 | - Begin Grants.gov registration.
- Gather & Adjudicate Feedback on first half of Project Narrative.
- Confirm PI
- Once registered with Grants.gov, create workspace and download application package and begin completing forms
- Continue considering personnel and/or partnerships required to respond
- If partnering with RI or any subcontractors, send subaward budget documents (downloaded from grants.gov application workspace) to RI or representative for completion
- Requests letter of support
- Draft Commercialization Plan
- Review PIER Plan requirements and begin to formulate plan
- Continue drafting Project Narrative - get feedback on completed sections
- Begin to formulate budget
- Begin Budget Justification Form
- Request biosketches for personnel and current/pending support lists
- .
- Complete detailed budget assembly.
- Build staff breakdown (employees, subcontractors, 1099.
- Gather supporting documentation and prepare staff section of Budget Justification.
- Send required forms to RI and/or subcontractors.
- Create first draft of the Commercialization Plan.
- Contact references and provide guidance for Letters of Support.
- Log-in to Grants.gov, create application workspace, and being completing forms.
- Request biosketches and current and pending support lists from key / senior personnel.Determine data management plan; if working with an RI, ensure that there is agreement on how/if data is to be shared
|
6 | - Register as SBC on SBIR.gov
- Follow up with RI or any subcontractors regarding required forms
- Follow up on requested Letters of Support
- Reach out to appropriate partners regarding PIER Plan
- Draft PI Biosketch and Current & Pending funding
- Finalize key personnel
- Continue drafting Project Narrative - get feedback on completed sections
- Continue to formulate Budget
- Continue to draft Budget Justification
- Draft Project Abstract / Summary
- Proof biosketches received so far
- Get feedback as necessary for Grants.gov and other required forms
- Divide time between creative aspects of writing Project Narrative and completing required form
- Complete draft of second half of Project Narrative. **Please note, "second half" equates to the following Project Narrative elements: Partners: Research Institutions (if applicable), Other Consultants & Subcontractors, Facilities, Other Resources, & Equipment, and Bibliography & References Cited.
- Complete Biosketch and current and pending support list for PI.
- Gather and adjudicate feedback on budget if necessary.
- Gather and adjudicate feedback on staffing breakdown if necessary.
- Gather supporting documents and write Facilities section of Budget Justification if applicable.
- Ensure that RI and any subcontractors have correct forms and necessary information to complete.
- Gather and adjudicate feedback on Commercialization Plan if necessary.
- Follow up and finalize Letters of Support.
- Complete forms as required by the FOA.
- Author Abstract / Project Summary.
- Review, provide feedback, and ask for updates on biosketches and current and pending support lists.Review DOE application checklist to verify all required forms
|
7 | Non-responsive feedback, if any, issue - If you receive non-responsive feedback, review, address the comments, and determine next steps
- Gather and adjudicate feedback on second half of Project Narrative.
- Finalize Grantsbudget.gov forms
- Get feedback on Budget
- Get feedback on Budget Justification
- Secure required forms from RI and any partnering organizations or subcontractors
- Secure Letters of Support
- Get feedback on Project Narrative
- Draft PIER Plan
- Finalize Commercialization Plan
- Continue to proof biosketches
|
8 | - Review Project Narrative for necessary edits and/or adjustments
- Review & finalize Budget
- Review & finalize Budget Justification
- Review DOE checklist to ensure all necessary forms completed
|
- Confirm employees, subcontractors, and consultants.
- Follow up with RI and/or subcontractors and consultants and finalize required forms.
- Finalize Commercialization Plan.
- Finalize Letters of Support.
- Finalize all forms required by the FOA.
- Finalize biosketches and current and pending support lists.
|
8 | - Add proprietary markings to Project Narrative.
- Finalize Budget Justification.
|
9 | Final review of application package and submit application. | 9 | Finalize & Submit application |